Solar Approval

Solar approval in Dubai comes from DEWA under the Shams Dubai programme, not from Dubai Municipality. A DEWA-enrolled consultant or contractor submits the solar PV design, DEWA approves it and quotes the connection fee, then inspects the finished system and installs the meter. We coordinate the design, the DEWA submission and the inspection so your solar permit moves without gaps.

Most people asking about solar approval are villa owners comparing installer quotes, or facility managers planning a larger rooftop system on a warehouse or tower. The questions are the same: who approves it, how big a system the building is allowed, and what happens to the power you don't use.

Any grid-connected solar system in Dubai needs DEWA approval before it's switched on, whatever its size. Surplus power is exported to the grid, and DEWA offsets it against your bill.

What is Solar Approval?

Solar Approval

Solar approval is DEWA's permission to connect a rooftop solar PV system to the Dubai grid. It runs under Shams Dubai, the distributed renewable resources generation programme, and covers the design review, the connection fee, the site inspection and the meter installation.

Only DEWA-enrolled solar consultants and contractors can apply, acting as the owner's agent. The approved capacity is limited to a share of the building's total connected load, and the panels and inverters must come from DEWA's eligible equipment list.

Shams Dubai Solar Approval Process

1. Feasibility check. We look at the roof and the building's connected load. DEWA caps capacity at a share of the total connected load and can set a lower limit for technical reasons.

2. Design submission. Site plans, the system design and equipment details go to DEWA. Panels and inverters must be on DEWA's eligible equipment list.

3. Design approval and connection fee. DEWA reviews the design and sends an estimate of the connection fee. Systems above 400 kW may carry extra grid-integration costs.

4. Installation. The enrolled contractor installs the system to the approved design.

5. Ready for inspection. DEWA is notified that the site is ready. Systems above 100 kW need a passed plant performance test first.

6. Inspection, meter and connection. DEWA inspects, the connection agreement is signed and the meter is installed. The system starts exporting.

Who Needs Solar Approval in Dubai?

Every grid-connected solar system needs DEWA approval before it is switched on. That includes:

Villa owners adding rooftop solar panels
Owners and facility managers of residential and commercial buildings
Warehouses, factories and schools with large roofs, where systems can go above 100 kW and need a plant performance test

Documents Required for Solar Approval

DEWA reviews the technical file your enrolled consultant or contractor submits. It should include:

Site plan showing the building and roof
Solar PV system design plans
Details of the proposed panels and inverters, all from DEWA's eligible equipment list
The building's DEWA account and connected load details
A plant performance test report before inspection, for systems above 100 kW

What Slows Down a Solar Approval

Most solar resubmissions come back to the same few issues:

Panels or inverters that are not on DEWA's eligible equipment list, which forces a redesign
A system sized above the allowed share of the building's connected load
Missing performance test results for systems above 100 kW
Site not ready when DEWA arrives for the inspection

Solar Approval FAQs

Quick answers to the questions villa owners and facility managers ask most:

Do I need approval to install solar panels on my villa in Dubai? Yes. Any grid-connected solar system needs DEWA approval under Shams Dubai before it is connected.
Who approves solar panels in Dubai? DEWA. Dubai Municipality does not issue the grid connection approval.
Who can apply for Shams Dubai approval? Only DEWA-enrolled solar consultants and contractors, acting as the owner's agent.
How much does DEWA charge to connect solar? DEWA sends a connection fee estimate after it approves the design. It depends on system size and site conditions.
Is there a size limit for rooftop solar? Yes. Capacity is limited to a share of the building's total connected load, and DEWA may set a lower cap.
What happens to the solar power I do not use? It is exported to the grid and offset against your DEWA bill.

Solar is one part of your building's DEWA file. For load changes, new connections and other DEWA NOCs, see our DEWA approval service. In master communities, check whether the developer needs to issue an NOC before installation; our Emaar NOC guide explains how that works.

Send us your DEWA account details and a roof photo, and we'll tell you what size of system DEWA is likely to allow.

Do you want to make an inquiry?

Feel free to reach out anytime

+971525717554
message
hello@dubaiapprovals.com
phone
Cheddar Cheese Tower (O-14 Tower) - 17th Floor - Business Bay - Dubai - United Arab Emirates
Explore Our Other Services