Solar approval in Dubai comes from DEWA under the Shams Dubai programme, not from Dubai Municipality. A DEWA-enrolled consultant or contractor submits the solar PV design, DEWA approves it and quotes the connection fee, then inspects the finished system and installs the meter. We coordinate the design, the DEWA submission and the inspection so your solar permit moves without gaps.
Most people asking about solar approval are villa owners comparing installer quotes, or facility managers planning a larger rooftop system on a warehouse or tower. The questions are the same: who approves it, how big a system the building is allowed, and what happens to the power you don't use.
Any grid-connected solar system in Dubai needs DEWA approval before it's switched on, whatever its size. Surplus power is exported to the grid, and DEWA offsets it against your bill.
Solar approval is DEWA's permission to connect a rooftop solar PV system to the Dubai grid. It runs under Shams Dubai, the distributed renewable resources generation programme, and covers the design review, the connection fee, the site inspection and the meter installation.
Only DEWA-enrolled solar consultants and contractors can apply, acting as the owner's agent. The approved capacity is limited to a share of the building's total connected load, and the panels and inverters must come from DEWA's eligible equipment list.
1. Feasibility check. We look at the roof and the building's connected load. DEWA caps capacity at a share of the total connected load and can set a lower limit for technical reasons.
2. Design submission. Site plans, the system design and equipment details go to DEWA. Panels and inverters must be on DEWA's eligible equipment list.
3. Design approval and connection fee. DEWA reviews the design and sends an estimate of the connection fee. Systems above 400 kW may carry extra grid-integration costs.
4. Installation. The enrolled contractor installs the system to the approved design.
5. Ready for inspection. DEWA is notified that the site is ready. Systems above 100 kW need a passed plant performance test first.
6. Inspection, meter and connection. DEWA inspects, the connection agreement is signed and the meter is installed. The system starts exporting.
Every grid-connected solar system needs DEWA approval before it is switched on. That includes:
DEWA reviews the technical file your enrolled consultant or contractor submits. It should include:
Most solar resubmissions come back to the same few issues:
Quick answers to the questions villa owners and facility managers ask most:
Solar is one part of your building's DEWA file. For load changes, new connections and other DEWA NOCs, see our DEWA approval service. In master communities, check whether the developer needs to issue an NOC before installation; our Emaar NOC guide explains how that works.