Third-party consultant approval is the independent design review Dubai Municipality requires for some high-risk work: shoring for buildings with four or more basements, special projects and any site next to a water body. An independent geotechnical consultant reviews and approves the design, and shares liability for it. We coordinate the third-party review and take the design through Dubai Municipality approval.
Third-party review usually surfaces when a project's basement count or location triggers it, often after the design team has already finished the shoring scheme. Without the independent review, Dubai Municipality won't approve the shoring, and excavation can't start.
Bringing the third-party consultant in alongside the design, rather than after it, keeps the review off the critical path.
Third-party consultant approval is the independent check Dubai's building regulations require on some designs before Dubai Municipality will approve them. Under Administrative Resolution No. 37 of 2021, which amended the bylaw on building requirements, shoring designs for projects with four or more basements, special projects and sites close to water bodies must be reviewed and approved by a third-party geotechnical consultant.
The reviewer is not a formality. They are jointly and equally liable for the shoring design with the design consultant and the shoring contractor, so their sign-off carries real weight with the authority.
1. Scope check. We confirm which design elements need independent review under the current Dubai building regulations.
2. Reviewer appointment. An approved third-party geotechnical consultant is appointed, independent of the design team.
3. Review cycle. The reviewer checks the shoring design and calculations, and comments are closed out with your designer.
4. Authority submission. The reviewed design and the third party's approval go to Dubai Municipality with the building permit application.
5. Site stage. Soil and material testing are carried out by labs approved by Dubai Municipality and accredited by EIAC, and the results are recorded for completion.
Dubai's building regulations require an independent third-party review for:
The third-party review carries legal weight, and testing has its own rules:
Quick answers to the questions developers and design consultants ask most:
Third-party review is part of the building permit, not a separate track. For the permit itself, see our Dubai Municipality approval service. Projects in Jebel Ali or DDA communities follow their own authority's rules; see our Trakhees approval and DDA approval services.
Send us the basement count, site location and shoring concept, and we'll tell you whether a third-party review applies.