Most delays with DEWA have nothing to do with DEWA being slow. Its published turnaround times are measured in working days, and it usually meets them. Projects lose time because a submission goes in through the wrong channel, the load schedule doesn't match the drawings, or the site isn't ready when the inspection is booked.
This guide walks through the DEWA approval process in the order it actually happens on a Dubai project: from the electricity and water NOC you need for a building permit, through LV design and load approval, substations, the connection invoice and inspection, to the day the meter is released. It covers new buildings, fit-outs and changes to existing supply such as an additional load or a new meter.
If you would rather hand the whole process over, our DEWA approval services cover the submissions on your behalf. If you want to understand what is happening at each stage, read on.
The short answer
DEWA approval is not one permit. It is a sequence run by a DEWA-enrolled consultant or contractor, never by the owner directly. For a new building it usually runs: building NOC (electricity and water), LV design approval, substation approval if the load needs one, a connection cost invoice, an LV inspection once the site is ready, and finally meter installation and supply release. DEWA publishes turnaround times of one to three working days for most of these stages. In practice the total time is set by how quickly your consultant can submit correct drawings and how quickly the site is ready for inspection.
Who can apply to DEWA
The first thing that surprises many owners is that they cannot submit most DEWA applications themselves. DEWA's builder services are open to enrolled consultants and contractors only. The owner appoints them; they hold the DEWA login, upload the drawings and receive the comments.
That has two practical consequences:
- Your consultant's DEWA enrolment matters. Before you appoint an engineering consultant or MEP contractor, confirm they are enrolled with DEWA for the category of work you need.
- The owner still pays. Connection estimates, invoices and the security deposit are issued to the project and paid by the owner through DEWA's payment channels, even though the consultant runs the application.
If you are not sure whether your project needs a consultant, a contractor or both, our guide to the role of engineering consultants in Dubai authority approvals explains who signs what.
Which channel your DEWA application goes through
DEWA receives applications through two different routes, and choosing the wrong one is a common reason for early rejection.
Projects that need a Dubai Municipality building permit
If your plot falls under Dubai Municipality, the DEWA electricity and water NOC is requested through the Dubai Building Permit System, not separately on the DEWA website. DEWA receives the request digitally and issues its NOC as part of the permit package, together with design approval and the delivery cost. DEWA's stated turnaround for this route is three working days from submission.
Projects in free zones and other licensing areas
If your project sits under another authority, such as Trakhees, the Dubai Development Authority or Dubai Integrated Economic Zones, the application goes through DEWA's own website or the Build in Dubai app. DEWA states two working days for the electricity NOC and three working days for the water NOC on this route.
Not sure which authority governs your plot? Start with our guide to which authority approves your Dubai project, because the DEWA channel follows from that answer.
The DEWA approval process for a new building, step by step
For a new building or a major extension, the sequence below is the one DEWA publishes for getting an electricity connection. Each stage depends on the one before it.
- Building NOC (electricity and water). Your consultant applies through the correct channel above. On DEWA's own route, the building NOC and the connection request are bundled into one application.
- LV design approval. The low-voltage design, including the total connected load and maximum demand, is reviewed. DEWA publishes one working day for loads up to 150 kW, two working days for 151 to 400 kW and three working days above 400 kW.
- Substation approval, where needed. Larger loads need an HV substation inside the plot. DEWA approves its location and size, with a stated turnaround of three working days, and later inspects the substation civil works once they are ready.
- Connection cost invoice. DEWA issues an invoice for the connection cost, which the owner pays through DEWA's payment channels. DEWA states this invoice is valid for one year from the date it is issued.
- LV inspection. Once the site is ready and the invoice is paid, the contractor requests an LV inspection. DEWA's published target is one working day from the request, with the result given on the spot: approved, or a snag list to close and resubmit.
- Meter installation and supply release. After a passed inspection, DEWA confirms the meter installation and the date the supply is released.
Water follows a parallel track for the NOC and connection, so your consultant should run both together rather than finishing electricity first.
The DEWA process for fit-outs
A fit-out inside an existing building runs through a lighter version of the same process. The application is made against the main project's DEWA reference, so the base building must already have its DEWA approvals in place.
DEWA lists these documents for a fit-out connection:
- A copy of the DEWA-approved total connected load and maximum demand schedule, and the MDB or SMDB schedule, for the main project.
- A load distribution schedule for the final distribution board.
- Lighting wiring layouts and power wiring layouts.
- A landlord NOC in DEWA's prescribed format.
- A site photo for the LV inspection submission.
DEWA states one working day for fit-out design approval, three working days for the invoice and one working day for the LV inspection. Power is switched on after the security deposit is paid, and DEWA combines the estimate and deposit into one invoice.
Fit-outs also need Civil Defence clearance for fire and life safety. That runs in parallel, not after DEWA. Our Civil Defence approval services page covers that track.
Changing an existing supply: additional load and new meters
Owners often need DEWA long after the building is complete: a villa extension that needs more power, a home office that needs a separate meter, or a retail unit that is upgrading its equipment.
These requests normally start with a no objection letter from the licensing authority, not with DEWA. For properties under Dubai Municipality, the contractor applies for the NOC to increase the electricity current or add a meter through the Build in Dubai platform. Once it is issued, the request goes to DEWA, which reviews the revised load schedule and, if approved, issues the invoice and books the work.
Two points save time here:
- Give a clear technical reason. Each request is assessed case by case, so a vague reason such as "more power needed" invites a return.
- Update the load schedule first. The revised connected load and maximum demand must match the equipment you are actually installing, or the inspection will not pass.
How long the DEWA approval process takes in practice
DEWA's published turnaround times are short, but they only measure DEWA's own review. The total time on your project is set by three things:
- Drawing quality. A return for comments restarts the clock on that stage. Mismatches between the load schedule and the single-line diagram are the most common cause.
- Site readiness. An LV inspection booked before the site is complete produces a snag list, not a connection.
- Other authorities. DEWA's NOC is one input to a building permit, and Civil Defence clearance often runs on a longer track.
For realistic end-to-end ranges across authorities, see our Dubai authority approval timeline guide.
Common reasons DEWA returns an application
- The application is submitted on the DEWA website when the project should have gone through the Dubai Building Permit System, or the other way round.
- The load schedule, distribution boards and single-line diagram don't agree with each other.
- The fit-out application is not linked to the correct main project reference, or the base building's approvals are incomplete.
- The landlord NOC is missing or not in DEWA's format.
- Inspection is requested before the connection invoice is paid or before the site is ready.
Most of these are avoidable with one review before submission. That review is the main thing an experienced approvals team adds.
After connection: completion and as-built approval
Connection is not the last DEWA step on a new building. Before the building completion certificate, DEWA needs to confirm the as-built installation. Our guide to DEWA completion certificate and as-built approval covers that stage.
If your project includes rooftop solar, that runs through DEWA's Shams Dubai programme with its own approvals. Our solar approval services page explains how it fits alongside the main connection.
Frequently asked questions
Can a property owner apply to DEWA directly for a building connection?
Not for builder services. DEWA's electricity connection and fit-out services are available to enrolled consultants and contractors only. The owner appoints them and pays the invoices.
Is the DEWA approval application free?
DEWA lists its builder eServices as free to submit. You pay the connection cost invoice and, where applicable, the security deposit, which DEWA issues after reviewing the application.
Do I apply to DEWA or to Dubai Municipality first?
For projects under Dubai Municipality, the DEWA NOC is requested through the Dubai Building Permit System as part of the permit, so you do not apply to DEWA separately at that stage. Projects under other authorities apply on DEWA's website.
How long is a DEWA connection invoice valid?
DEWA states that the connection cost is valid for one year from the date the invoice is issued.
What happens if the LV inspection fails?
DEWA gives the result on the spot. A failed inspection comes with a snag list, which the contractor closes before requesting the inspection again.
Do I need DEWA approval for a fit-out in a rented office?
Yes, if the fit-out changes the electrical installation. The application is linked to the building's main DEWA reference and needs a landlord NOC in DEWA's format.
Getting your DEWA approvals moving
If you are planning a new building, a fit-out or a change to an existing supply, send us your plot or unit details and the scope. We will confirm which channel your DEWA application belongs in, what drawings and schedules it needs, and how it fits with your other authority approvals. You can contact our team here.